Memo
To: Town Board - Town of Wappinger
Attention: SupeiVisor Constance O. Smith
From: Peter J. Paggi
cc: Hon. Vincent Bettina, Councilman
Hon. Joseph Paoloni, Councilman
Hon. Joseph Ruggiero, Councilman
Hon. Robert Valdati, Councilman
Planning Board
Elaine Snowden, Town Clerk
Albert P. Roberts, Esq.
Graham Foster, Highway Superintendent
Mark Ueberman, Acting Zoning Administrator
Lawrence J. Paggi, P.E., P.C.
Date: OS/27/99
Re: Meadowwoods Subdivision
Section 1, Parcel 1
Comments:
Dear Supervisor Smith and Board Members:
This office has calculated the amount of the bond for roadway and utility construction for Section 1,
Parcel 1 of the Meadowwoods Subdivision. A copy of said bond calculation is enclosed herein.
The total construction value of the work (adjusted to May,1999 dollars) is $ 209,018.00. It has been the
practice of the Zoning Administrator's office to add 20% for necessary administrative costs, which
would make the total $ 250,822.00. The inspection fee forthis portion of the project is $ 6,270.00.
Please feel free to contact this office if you have any questions or comments.
Thank you.
Cad1 \DA TA\DRAWINGS\DOCUMENTSmeadowwoods.bond.5.27.99
RECEIVED
JUN 0 1 1999
. Page 1
ELAINE SNOWDEN
roWN CLEAt<
,.
BOND CALCULATION
MEADOWOOD SUBDIVISION
SECTION 1, PARCEL 1
MAY 27TH, 1999
ITEM QUANTITY UNIT COST TOTAL COST
~ CLEARING/GRUBBING 1.15 ACRES $ 6,000.00/AC $ 6,900.00
~ ROUGH GRADE 1,925 C.Y. $ 5.00/CY $ 9,625.00
~ STORM SEWER
. Pipe (18" Dia. HOPE) 1,183 L.F. $ 24.00/LF $ 28,392.00
. Catch Basins 12 EACH $ 800.001EA $ 9,600.00
. End Sections 2 EACH $ 250.001EA $ 500.00
. Underdrain 430 L.F. $ 7.00/LF $ 3,010.00
. Detention Pond lEACH LUMP SUM $ 5,000.00
~ FOUNDATION 963 CY $ 22.00/CY $ 21,186.00
~ BINDER COURSE 430 Ton $ 65.00ITON $ 27,950.00
;,. TOP COURSE 300 Ton $ 65.00ITON $ 19,500.00
;,. BERM 2,200 L.F. $ 5.00/LF $ 11,000.00
;,. DCDPW ENTRY lEACH $ 11,500.00/LS $ 11,500.00
;,. MONUMENTS 8 EACH $ 200.001EA $ 1,600.00
;,. BACKFILL 890 CY. $ 5.00/LF $ 4,450.00
;,. TOPSOIL/SEEDING 0.6 ACRE $ 8,000.00/AC $ 4,800.00
;,. STREET TREES 24 EACH $ 150.001EA $ 3,600.00
;,. SIGNAGE 2 EACH $ 200.001EA. $ 400.00
~ EROSION CONTROL LUMP SUM LUMP SUM $ 1,000.00
GROSS SUBTOTAL $ 170,013.00
GROSS SUBTOTAL WIENRADJUSTMENT $ 209,018.00
TOTAL WITH 20% ADMINISTRATIVE FEES $ 250,822.00
INSPECTION FEES $ 6,270.00
ENR ISSUE - 05/17/99 = 6005.76