August 30, 1999
Mr. Robert Juliano
Commission Chairman
156 W. Main Street
Wappingers Falls, NY 12590
Subject:
Progress Report
Phase 3 Expansion
Town of Wappinger
Dutchess County, New York
Dear Chairman Juliano:
Enclosed please find a copy of the progress report for the month of August 1999 for your.
information and files.
If you have any questions, please let me know.
Very truly yours,
EUST ANCE & HOROWITZ, P.c.
~---
Inder). Kumar, Ph.D., P.E.
Chief Executive Officer
Enclosures:
cc: leif Jensen, Hon. Chairman - TMSC
louis Miller, Plant Administrator ~ TMSC
Anthony Quartararo, Commission Attorney - TMSC
James Sedore, Commission Accountant
Matthew Rudikoff, Env. Administrator - TMSC
Constance Smith, Supervisor - Town of Wappinger
Mark Rowe, Chief Operator - STES
IJKlje
twn-wpngld335
P.O. BOX 42
CIRCLEVILLE. NY 10919 914-361-4541 FAX 914-361-1045 .
.^
8:,30-1999 5:20PM
FROM
Progress Report for August 1999
Town of Wappinger - Phase 3 Expansion
05/
P.2
f!L~
'.
~
Tri-Municipal Sewer Commission
August 30, 1999
The following work was accomplished during the month of August 1999:
1. Field work for topographic survey and location of the sewer line and force main is 99
percent complete.
2. Prepared easement maps for force main and gravity sewer constructed through private
lands and depressed sewer.
3. Received prices for test boring in the creek from Melick and Tully. The price for test
boring is $6,000 for mobilization and demobilization plus $2,800 per day for boring.
Minimum 5 days for 6 to 8 holes (total cost $20,000).
4. Contacted General Boring ,of Prospect, Connecticut. Site meeting with General Boring
for test boring in the creek.
5. Checked Village pump station piping. Modifications to piping is required and is being
designed.
6. Reviewed treatment plant plans for design of proposed grit chamber, clarifier, chlorine
contact tank, etc.
7. Reviewed piping at the wastewater treatment plant for connection to new piping.
Planned for the month of September 1999:
1. Complete field survey 'work for secondary clarifier and chlorine contact tank.
2~ Prepare sewer plans and profi les.
3. Design modifications to the existing Village pump station.
4. Col/ect information on new secondary clarifier and new grit chamber.
5. Design installation of muffin monster type Comminutor.