. PAGGI & MARTIN
Consulting Engineers & Land Surveyors
ofJO
-
/
..
,
AECEIVt:D
AUG 2 1 1996
StJPERVISOFrSO
TOWNOFWAPPI:~~
54-56 Main Street
Poughkeepsie, New York 12601
9 1 4-47 1 - 78 9 8
August 19, 1996
Town Supervisor
Town of Wappinger
P.O. Box 324
Wappingers Falls, New York 12590
Reference:
Constance O. Smith
All Angels Hill
Sewer Main Replacement
Dear Supervisor Smith:
Attention:
As reported at the July 17, 1996 Workshop, the 800' of existing sewer
main on the west side of All Angels Hill Road to the south of Kent Road
is in danger of eminent collapse. We were instructed to look at two (2)
alternative methods for replacing this line.
The first method was physically installing a 8" pipe and one (1) manhole
in the existing ditch line. To do this, we analyzed the cost of
replacement of 800' of 8" PVC, including hooking up the existing lateral
connections.
In analyzing the site, I noticed that the pipe is located in an existing
easement located on the west side of All Angels Hill Road. This
easement also has in it an existing water main and utility line.
Therefore, replacement of the line would be rather difficult.
We also noticed that the residents have planted numerous shrubs and
trees in the easement that would need to be removed to replace the
pipe.
I have asked the Town Attorney to render and opinion whether or not
we would have to replace the trees upon completion of construction.
He has indicated to me that, in all likelihood, we would not have to
replace them. Therefore, the cost estimate that you see below reflects
only topsoiling and seeding the easement, and NOT replacing the trees
and shrubs.
Joseph E. Paggi,Jr., P.E.
Ernst Martin, Jr., P.E., L.S.
ro
~~ printed on recycled paper
Constance O. Smith
RE: All Angels Hill
- 2 -
August 19, 1996
';
If the Town Board made an administrative decision that the trees and
shrubs should be replaced to whatever degree, those cO'sts would be in
addition to the costs listed below.
Our analysis indicates the project cost to replace the pipe is as follows:
Construction Cost $ 86,000.00
Contingency $ 9,000.00
Total Construction Cost $ 95,000.00
Engineering Design $ 10,000.00
Engineering Inspection $ 6,000.00
Legal Fees $ 5,000.00
Map, Plan & Report $ 2,000.00
I TOTAL COST I $118,000.00
, ,
.
Constance O. Smith
RE: All Angels Hill
- 3 -
August 19, 1996
';
The second alternative for replacing the pipe is to Insituform the pipe.
To determine this cost, we contacted Sal Randazo of Insituform
Metropolitan, and he has supplied us with the following information.
Construction Cost $ 70,000.00
Contingency $ 7,000.00
Total Construction Cost $ 77,000.00
Engineering Design $ 10,000.00
Engineering Inspection $ 6,000.00
Legal Fees $ 5,000.00
Map, Plan & Report $ 2,000.00
I TOTAL COST , $ 100,000.00
In would be our opinion that the Town should pursue the second option
using the Insituform method and authorize the preparation of the
appropriate Map, Plan and Report.
Very truly yours,
~~gc;~~
JEP:law