PAGGI & MARTIN
Consulting Engineers & Land Surveyors
(7/JrJ
54-56 Main Street
Poughkeepsie, New York 12601
9 1 4-47 1- i8 9 8
October 13, 1993
RECEIVED
Or. T 1 4 1993
StJPERVISOR'S OFFICE
TOWN OFWAPPINGER
Town Board
Town of Wappinger
P.O~ Box 324
Wappingers Falls, New York 12590
Attention: Supervisor Constance O. Smith
Reference: Wappinger Sewer Transmission/Treatment Improvement Area
Phase 1, Contract No.1 (Pillari Bros.)
Phase 1, Contract No.2 (G.A.L.S. Inc.)
Dear Supervisor Smith:
I would like to be placed on the October 25, 1993, Town
Board Agenda to discuss the above.referenced projects. I
have listed below a synopsis of these pertinent items.
A. PHASE 1. CONTRACT NO.1 (PILLARI BROS):
Pillari Bros. will be constructing Cased Crossing No. 1
(Route 9D) within the ensuing weeks, as part of their
contract. Does the Town Board wish to utilize this
casing for a twofold crossing?
As in the Route 9 crossing, our Wappinger Sewer
Transmission/Treatment Improvement Area transmission main
would be on the bottom, and a a" ductile iron water main
would be suspended at the top for future use by the Town.
Pillari Bros. has given me a price of $8,300.00 to supply
all labor, equipment and material to install 102 linear
feet of 8" D.I.P. Class 52 with field lok gaskets within
the proposed 60" casing (see enclosed letter).
lL. PHASE 1. CONTRACT NO.2 (O.A.L.S. INC.):
Attached is Change Order No. 5.. (5A,. 5B, & 5C) which
involves the use of the Dutchess County Sheriff and Town
of Wappinger patrol" vehicles for maIntenance and
protection of traffic as deemed vital by the Dutchess
County Department of Public Works.
Joseph E. Paggi,Jr., P.E.
Ernst Martin, Jr., P.E., L.S.
@ printed on recycled paper
October 13, 1993 Page Two
Town Board
Town of Wappinger
P.O. Box 324
Wappingers Falls, New York 12590
Attention: SupervIsor Constarice o. 'Smith
Reference: Wappinger Sewer Transmission/Treatment Improvement Area
Phase I, Contract No.1 (Pillari Bros.)
Phase I, Contract No.2 (G.A.L.S. Inc.)
Change Order No. SA:
Credit to Town of Wappinger (decrease of Contract amount)
for utilizing one (1) Dutchess County Sheriff and Town
Patrol vehicle for maintenance and protection of traffic
during construction in lieu of union flagperson:
Labor. . . . . . . . . . . . . $5,230.40
Town Patrol Vehicle. ... 780.00
$6,010.40
change Order No. SB:
Payment owed to Dutchess County Sheriff for maintenance
and protection of traffic during course of construction:
$3,215.30
Change Order No. SC:
Payment owned to Town of Wappinger for usage of Town
Patrol vehicle by Dutchess County Sheriff during
construction to insure maintenance and protection of
traffic.
$ 780.00
.. .
October 13, 1993 Page Three
Town Board
Town of Wappinger
P.O. Box 324
W~ppingers Falls, New York 12590
Attention: Supervisor Constance o. smith
Reference: Wappinger Sewer Transmission/Treatment Improvement Area
Phase 1, Contract No.1 (Pillari Bros.)
Phase 1, Contract No.2 (G.A.L.S. Inc.)
Change Order 5A, 5B and 5C will result in an overall
savings to the Town of:
G.A.L.S. Inc. Credit. . . . . . $ 5,230.40
D.C. Sheriff Payment .... $ 3,215.30
2,015.10
+ 780.00
$ 2,795.10
Town Patrol Vehicle
If you have any questions or comments, please do not
hesitate to contact me.
Very truly yours,
~~~
James F. Bedore
Project Engineer
JFB:law
cc: Ann Buckley, Town Comptroller