1984-10-27
~, ...~..
ft& l\.t SUPERVISOR'S OFFICE
\J"'O MILL STREET. P.O. Box 324
WAPPINGERS FALLS, N Y. 12590
OF WAPPINGER
FRANK J. VERSACE
SUPERVISOR
August 27, 1984
Mr. Joseph Marcogleise, P.E.
Senior Sanitarj Engineer
N.Y.S. Dept. of Environmental Conservation
202 Mamaroneck Avenue
White Plains, New York 10601
Dear Mr. Marcogleise:
I would first like to take the opportunity to thank you for meeting with us
on August 7th to discuss the five sewage treatment plants operated by the
Town of Wappinger. I would also like to thank you for extending the date for
our engineer's report evaluating these five systems until November 1, 1984.
As per our agreement I am forwarding to you, prior to September 1st date, an
evaluation of action that has been taken, or is at present scheduled to be
taken, to comply with your letter of June 4, 1984.
Oakwood Knoll Seweraae Svstem
-
1. The problem wi th high' flows, frequent by-passing and overflowing of tanks
has been addressed and will in the future be adressed in the following
manners:
An infiltration study had been conducted last year and some of the problem
was corrected. We are aware that this is an on-going program and have
directed our Town Engineer to investigate the location of the more serious
problems within the Oakwood District in order that he might give us a price
and we might budget the corrective action necessary to resolve the problem
in the years 1985 and 1986. In addition we have directed, and Camo Pollution
Control has completed, the installation of a splitter box prior to the discs
that will balance the flow and reduce the frequency of overflowing of the
disc tanks. We realize, however, that the final solution to tank overflow
will only be eliminated completely with the correction of the high flows;
and, therefore, we are committing to extensive investigation and correction
of infiltration as we uncover it.
2. Regarding the rapid sand filters, we plan to do the following:
A. In our 1985 budget we will be including funds for an extensive spare
parts list to reduce the mechanical downtime to an absolute minimum. Our
operators have advised us that this will contribute considerably toward
keeping the filters running on a continual basis.
B. In addition, we have been advised by our engineers and operators that,
again, the correction of the infiltration and inflow problem will also have
Mr. Joseph Marcogleise
Senior Sanitary Engineer
-2-
great impact upon this problem and, in fact, for all practical purposes
along with the spare parts, resolve the problem.
C. Again, as we stated above, in the near future we will be receiving a
report from our engineer as to the area and the expense involved in cor-
recting the infiltration at the Oakwood Plant and, in discussions with you,
determine a reasonable and economic time frame in which to take the correc-
tive action which they recommend.
Wildwood Sewer System
1. The problem of high flow is evident and we have included funding in our
1983 budget to start a study to indicate the areas of greatest concern
along with an estimate of cost to correct the infiltration in these areas.
Again, as with Oakwood, we will be budgeting for corrective action in our
'85 - '86 budgets.
2. To forestall a deterioration of the facility due to age, our operators have
been painting, scraping, replacing the fencing as needed and replacing grates
at the facility which should go a long way toward keeping the deterioration
to a minimum.
Royal Ridqe
1.
As with all the facilities we operate, there is a problem with high flows.
Infilitration inflow investigations will be budgeted in our 1985 budget for
this facility. In the interim, although no money was able to be budgeted
due to financial contraints at this plant, the operators have found by
systematic visual observation of manholes at night what appears to be a
major infiltration of what could well be water from the central water system
into the sewer lines. The amount this correction will improve the situation
will only be determined after the correction has been taken in the coming
weeks. We will, of course, keep you posted on our progress in that area.
~
The sand filters have been investigated and the interior perimeter walls
have been replaced. In addition, the ditributors have been repaired to
the point of being quite functional. The overall rebuilding of the sand
filters is awaiting our engineer's evaluation of the existing sand, which
is between 24 and 30 inches deep, by sieve analysis in order to determine
whether it is still capable of functioning as required. In addition, our
engineers and operators are experimenting with planting sand filters with
bull rushes in order to prevent clogging and allow for treatment with
considerably more flow onto a sand bed than is normally allowed by current
design. This experimentation is going on at the Dutchess Park Plant in the
Town of Fishkill and some concrete results should be in evidence in the
spring of 1985--at which time we would like to meet and discuss with you
the possibility, if this system seems feasible, of planting the entire bed
with the bull rushes; or, if it is not feasible, working out an economic
schedule with you to completely rebuild the beds if that is necessary.
3.
The settling tank skimmer will be repaired by November 1, 1984. In addition,
our engineers are investigating some type of dissipation weir in order to
eliminate short circuiting within the tank. They will have their findings
Mr. Joseph Marcogleise
Senior Sanitary Engineer
-3-
to us prior to November 1, 1984.
4. In order to improve disinfection during high flow, our operators have
recommended and we have approved the installation of a spare chlorinator
and crock at the facility to be used manually when high flows occur.
This installation should be completed by December 31, 1984. It will be
used until such time as the main cause of the problem, i.e. excessive
infiltration inflow, has been corrected.
Rockingham Farm Sewage System
1. Here again we are faced with the problem of high flows at the facility.
Again, we will have our engineers, as part of their study to be forwarded
to you by November 1st, estimate what work is necessary and the time-
frame in which it will be done in order that we can correct this problem.
We will also have them investigate what work was done under the Tri-Municipal
Contract which should have corrected the problem but has, obviously, not
resolved the problem fully. I would like at this time, also, to have my
engineer and operators discuss with you the possibility of installing by-
passes to aid in resolving the effect of the infiltration inflow probl~m
on the plant at Rockinqharn. In the past, a by-pass was permitted and
constructed. This, althouqh not a substitute for correcting infiltration
inflow problems, does appear to be a way in which minimum affect on the
stream and the plant occurs until such time as the infiltration inflow
is corrected.
2. The better disinfection system requested in your letter will be resolved
by funds being placed in our 1985 budget by the installation of a by-pass
line from the existing plant chlorinator directly to the large external
sand filter chlorine tank. In this way, at all times, properly chlorinated
effluent would discharge to the center of Sprout Creek. In addition, in
regard to the plaugging of the sand beds as we mentioned earlier, we are
looking into an evaluation of the effects of planting the sand filters
with bull rushes in order to prevent plugging of the sand.
Fleetwood Manor Sewerage System
1. As mentioned prior, reduction in flows is a necessity also at this facility.
Our engineer will be adivsing you as per their November report as to what
action will be taking place to correct this problem.
2. A back flow preventer on the potable water supply system to the plant
will be installed prior to December 31, 1984.
3. Both settling tanks have been rebuilt.
4. The report on the infuent structure is being developed by our engineers at
present and the completed report and design of the proper structure should
be completed by December 31, 1984 for inclusion and construction in our
1985 budget year.
.
~
Mr. Joseph Marcogleise
Senior Sanitary Engineer
-4-
5. The flow meter has been ordered and will be installed upon arrival.
6. Fencing has been installed around the entire facility. The area has
now been chained off to all vehicles and routinely checked by the
Wappingers Security Patrol to ensure a minimum of vandalism at the
facility.
I hope this information answers any questions you might have regarding the
facilities and indicates that, in fact, we are trying as we stated at our
meeting to resolve all the problems we have with sewer and water as quickly
as funds permit. If you have any questions regarding this matter, please con-
tact myself, my engineer or my operator.
Very truly yours,
~~A,(,L Ilt',CLC~~L
Frank Versace
Supervisor
Town of Wappinger
FV/fh